JULY 2014
Timeline of Site Improvements

July 2014
The Rutherford County Board of Commissioners approve funding for site improvements at Gateway West Commerce Park.

August 2014
The Rutherford County Board of Commissioners approve Civil Engineers to begin design of site improvements for Gateway West Commerce Park.

November 2014
The Rutherford County Board of Commissioners approve lowest bid for site improvements at Gateway West Commerce Park.

December 2014
Grading contractor mobilizes at Gateway West Commerce Park.

April 2015
Site grading activities at Gateway West Commerce Park are complete!